A Dillon Consulting study of Wellington Road 46 covers Brock Road South through Aberfoyle, between Wellington Road 34 and Gilmour Road. Dillon Consulting

PUSLINCH – A Wellington County-commissioned study has identified keeping four lanes on Brock Road (Wellington Road 46) and adding traffic calming measures as the preferred option, after the township has pushed for years for reduced lanes through Aberfoyle.

Two other options closest to what the township wanted – three lanes and on-street parking, either by repainting or rebuilding the road – were passed over in the Dillon Consulting study, along with leaving the road as is.

An open house on the latest recommendation for the road was held at the Puslinch Community Centre on Nov. 3 and attended by about 50 people.

According to Dillon’s presentation materials, reducing the road to three lanes would create traffic queues up to 1km long and push up to 580 vehicles onto surrounding roads during peak hours. Gilmour Road would need upgrading to handle the diverted traffic.

County engineer Don Kudo stated in an email to the Advertiser that feedback received “generally” suggests a preference for increased police enforcement, rather than modifying the road.

“Some attendees noted concerns that roadway modifications could impede traffic flow, worsen vehicle queuing or divert traffic onto adjacent roads such as Victoria Road and Watson Road,” Kudo said.

Attendees suggested an additional mid-block crosswalk, raised crosswalks at intersections and roundabouts, optimized traffic signal timing, and additional sidewalks and/or cycling lanes could address pedestrian safety, according to Kudo.

Feedback about on-street parking was divided, Kudo said. Some said it’s not needed; the township suggested it could stimulate business.

“Suggestions also included deferring any changes to Wellington Road 46 until after the Morriston bypass is completed,” Kudo added.

Second study of its kind

Wellington Road 46 runs from Maltby Road, at the south end of Guelph, through Puslinch to Highway 401.

Wanting a more pedestrian-friendly community, the township asked in 2019 for one lane each way, a centre turning lane and parking during the reconstruction of Wellington Road 46 from Wellington Road 34 to McLean Road in 2019-20. A reduction in lanes would have amounted to repainting the road rather than physically altering it.

The project included a four-lane reconstruction, and the construction of two-lane roundabouts where the road meets Gilmour Road and Wellington Road 34.

The county’s roads committee and council decided against reducing the lanes at the time, but ordered a traffic study after the reconstruction to review whether the lanes could be reconfigured.

That study, completed by Dillon Consulting in 2021, suggested a “road diet” would result in Gilmour and Victoria roads needing upgrades to absorb diverted traffic. County staff noted those upgrades would be at Puslinch’s expense and the change would require an environmental assessment.

The county opted to undertake a second study either after the Morriston bypass was in place or the Highway 6/Hanlon Expressway midblock interchange was complete.

Meanwhile, Brock Road from Wellington Road 34 to Gilmour Road was designated a Community Safety Zone, Puslinch hired a crossing guard and the county implemented safety measures on the roadway with digital radar signs and better crosswalk markings, among others.

With the interchange completed in 2025, Puslinch asked for the second study.

Final recommendation expected in January

In the latest study, Dillon considered survey responses, feedback from an advisory group, traffic and collision data, and forecasted future traffic volumes, among other things.

There were four options evaluated in the study: leaving the road as is; narrowing inner lanes with a centre buffer; repainting the road to three lanes, including a centre turning lane, with on-street parking; and rebuilding the road with three lanes, parking and wider sidewalks.

The consultant rated each option from least to most preferred in four categories, including transportation, engineering/cost, socio-economic and environmental.

The second option explored – keeping all four lanes with traffic calming – was the most preferred in the study.

A concept design shows inner lanes narrowed by 20cm each, and a 40cm painted buffer between. However, the final design could change.

According to Dillon’s presentation materials, there’s potential to slow traffic without affecting road capacity, pedestrian comfort would be improved, engineering complexity and cost would be moderate, and it avoids expanding the overall size of the road.

It's expected the study will be presented to Puslinch council before the end of the year, with a final recommendation to be presented to the county’s roads committee in early 2027.

Jordan Snobelen profile image
by Jordan Snobelen

Get Local News Delivered

Join our community of readers and get weekly updates on what matters most in Wellington County.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More