Construction on Allan Street East wraps up

Construction wraps up – Construction on Allan Street East here is close to finishing for the season. The work underground is done, the curbs and sidewalks poured and the first layer of paving was done on Nov. 15 – the second coat will need to await the arrival of spring.

Landscaping is still to be done to allow the tenants back into the parking lot and beautify the street. A traffic light sensor will need to be replaced.

Site inspector Jeremy Gibson, right, and the crew from the Murray Group awaited the next load of asphalt to pave Allan Street East in Clifford on Nov. 15.                                         

Contributor