Allan Street project underway

Drew Mochrie profile image
by Drew Mochrie
Allan Street project underway
Street construction - Reeves Construction Ltd. of Mount Forest began removing pavement on July 28 for a reconstruction project on Allan Street East in Clifford. Photo by Bonnie Whitehead

CLIFFORD - Another round of construction in Clifford is underway. Allan Street East will be under construction from July 26 to October.

A letter delivered to residents in the impacted areas by Jeremy Gibson, site inspector for Triton Engineering Services Limited, states, “The street will be closed to through traffic during the construction period. Local access will also be interrupted during this period.”

Construction staff will be assisting with garbage and recycling to assure the bins are moved to a designated location for pick up Tuesday mornings.

Reeves Construction Ltd. of Mount Forest will be installing a new water main, new storm drains, new curbs and gutters, and new sidewalks.

The Clifford Rotary Celebration Square municipal parking lot will be spruced up to complete the street project.

On July 27, a surveyor took measurements and left pink stakes planted in the ground. On Wednesday, July 28, the traffic light signals were altered to cycle every 15 to 30 seconds. The southeast green light was also repaired as well.

Drew Mochrie profile image
by Drew Mochrie

Get Local News Delivered

Join our community of readers and get weekly updates on what matters most in Wellington County.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More